NEWS & MEDIA

31 May 2022
Construction on process update - May 2022

As we have coming to an end of May the weather in Ho Chi Minh city is getting wet and overcast gradually. The project is still well managed as planned and 90% of 2nd level of floor slab has been casted. Below are some recent pictures taken for your viewing.



Bird's eye view of DEFINE. Casted 90% for Level 2.



Installing propping for slab of Level 3 & column works for Level 2 to Level 3.




Site Activities.